Wednesday, April 17, 2013
Great progress has been made over the past few weeks including framing of offices, insulating critical areas including some interior walls, and drywall/painting of the first of many offices. Open spaces have been designed, furniture ordered, and plans are moving foward for a june/july occupancy.
We started using the warehouse to serve as our premier distribution center. Meanwhile, multiple trades are working simultaneously including HVAC, landscaping, plumbing, and finishing. On the outside of the building the grounds are being cleaned up and graded; the exterior of the building is being finalized. Within the next couple weeks, ceilings will be suspended where applicable, fixtures will be installed, and the original solid wood doors, which were saved during the initial de-construction, will be re-hung.
Friday, March 1, 2013

I saw 3 different trades at work this morning, including HVAC, framing and drywall, and electrical. The image below shows ductwork beginning to be installed in the 30,000 square foot showroom & conferencing center. Other areas of the building are also having ductwork installed and eventually this will be all tied together into a well planned HVAC system.
Framing of some of the private offices has also begun. At the accelerated pace that has been occuring, these private offices should be wired and drywalled within a short period of time.
Friday, February 15, 2013
message from Ron Hux:
In December we started on the interior build-out of
our offices. Since December we’ve made significant progress on the infrastructure including welding new roof trusses where HVAC units will be sitting, installing a new roof on
the showroom area to meet LEED requirements and placing sky lights and a new
roof structure in a small area in the showroom. I made a decision early on
not to use the existing plumbing so all new pipes had to be put in the floors. In addition, we removed a block wall to expand the accounting area and installed the fire
sprinkler system.
![]() |
| interior views highlighting build-out and the glass enclosures of our 4000 sq. ft. addition |
With all this behind us now, the crews are concentrating on
framing and building out the space. We expect this to progress rapidly. By mid-March framing should be complete and drywall should begin to be hung.
![]() |
| left to right: the delivery of drywall has begun, new roof trusses, interior view looking northeast |
Thursday, December 27, 2012
Finishing the year strong
Years ago I used to participate in long distance running races and olympic distance triathlon's. My training regiments included "track work-outs" with like minded individuals. I'll always remember the coach would bark out commands offer encouragement as we crossed the finish line on every distance set. " Finish strong. Don't slow down. Run all the way through the finishline."
Well, here we find ourselves at the end of 2012 and we have multiple crews working hard. One crew works at finishing off the main entrance (left) while another crew works at setting the side entrance (right). Simultaneously, window and door frames are being added to the addition.
Hard and persistent work does lead to noticeable progress. Commenting on my running days: after each set, we'd get 15 seconds rest and do it all over again. It amounted to quite a workout during that 1 hour and in the end we all turned out better, stronger and faster. Not surprisingly, one of the participants was a part of the 2000 summer Olympics team.
Beginning in the new year, these crews will continue to work hard on this 2nd phase of our project. Follow our progress regularly as we share stories on the transformation of this once aged building into our new corporate campus with state of the art features, a beautiful showroom and designer center, LEED certification, and more.
Well, here we find ourselves at the end of 2012 and we have multiple crews working hard. One crew works at finishing off the main entrance (left) while another crew works at setting the side entrance (right). Simultaneously, window and door frames are being added to the addition.
Hard and persistent work does lead to noticeable progress. Commenting on my running days: after each set, we'd get 15 seconds rest and do it all over again. It amounted to quite a workout during that 1 hour and in the end we all turned out better, stronger and faster. Not surprisingly, one of the participants was a part of the 2000 summer Olympics team.
Beginning in the new year, these crews will continue to work hard on this 2nd phase of our project. Follow our progress regularly as we share stories on the transformation of this once aged building into our new corporate campus with state of the art features, a beautiful showroom and designer center, LEED certification, and more.
Tuesday, December 4, 2012
Building Progression
These are exciting times. Multiple trades are working simultaneously. One such example is that the window and glass company has carefully measured each window and installed energy efficient glass in all window openings - which will serve as another contributing factor in our planned LEED certification.
Friday, October 19, 2012
Constuction continues with progress on our 4000 square foot addition and the front entrance. The footers were poured and walls were erected. Earlier this week the trusses were placed and the front entrance was beginning to take shape.
The more this project comes together, the easier it is to imagine what the exterior will look like.
Meanwhile, the warehouse which was completed months ago is now being used to warehouse product that will be used in our offices and showroom.